Click on the City Logo to go Home Click on the City Logo to go Home Click on the City Logo to go Home
Two Rivers Convention Center Hot Topics
City Council Contact Us Jobs Breaking News Recreation Visit Grand Junction
 
Search:
 
 

Construction Begins on Phase 3 of 29 Road Overpass

Welders attach additional steel to be driven into the ground for the ramp connecting to the overpass. Crews are filling in the median between I-70B and the frontage road. Westbound traffic will shifted for construction of the middle pier.

The south side of I-70B is the location for the ramp bridge that will connect to the overpass. Pile driving for the ramp and mainline bridge will continue for six weeks. The steel piling will provide support for the bridge foundation.


August 16,2010 Project Newsletter

For more 29 Road and I-70B photos and updates check:

or

 

Construction Complete on the
North and South Street Phases


  

The 29 Road and I-70B Interchange project is a key component in the transformation of the 29 Road Corridor into a major link in the Riverside Parkway transportation network.  This project will construct an overpass to extend 29 Road over the Union Pacific Railroad tracks and I-70B.  The new overpass and I-70B Interchange is part of the 29 Road corridor improvements that will eventually connect Highway 50 with Interstate 70, and combine with the Riverside Parkway and 24 Road to become a beltway around the City.  The 29 Road street section will be 5 lanes wide (4 travel lanes and a center turn lane), and will include bike lanes and attached concrete sidewalks.

Planning and design work on the project began early in 2005.  The first step was to complete CDOT’s 1601 Interchange approval process and environmental assessment.  After receiving approval from CDOT for a new interchange on I-70B, the final design, Right-of-Way acquisition, and utility coordination got underway and continued through late 2008.  During this same time, the application process with the Colorado Public Utilities Commission (CPUC) authorizing a new grade separated rail crossing, along with negotiations with the Union Pacific Railroad (UPRR) were ongoing.  The CPUC authorization for a new rail crossing was obtained in June 2009 and a final Overpass Agreement with the UPRR was signed in November 2009.

Construction of the project was separated into four phases:  Irrigation Phase, North Phase, South Phase, and the Interchange Phase.  This approach provided several benefits including: allowing construction to continue while UPRR negotiations were ongoing and while applications for grant money were pending, took advantage of a favorable bidding environment, allowed for more local contractor involvement, minimized disruption to the public and adjacent property owners by constructing the streets that will serve as detour routes during the Interchange Phase.

This final phase of the project will consist of approximately 2.2 miles of new or reconstructed streets.  The project also consists of construction of a 7-span, 779 foot long concrete roadway bridge; a 5-span, 322 foot long concrete roadway bridge; construction of 67,000 square feet of retaining walls; and approximately 6,300 feet of storm drain, sewer, and irrigation pipe.

This phase started June 7, 2010, with completion by November 1, 2011.




In February 2010, the City of Grand Junction and Mesa County were awarded $3.2 million from the Colorado Department of Local Affair's Energy and Mineral Impact Assistance Program. This state program is designed to assist local and state agencies in Colorado that are experiencing social and economic impacts resulting from the development, processing, or energy conversion of minerals or mineral fuels. This grant money will be combined with local funds contributed equally by the City and Mesa County to construct the Interchange Phase.

Construction Phases Exhibit for 29 Road and I-70B Interchange Project

The North Phase - was awarded to Sorter Construction for $1,349,423. They have constructed sections of Teller Avenue, Melody Lane, Sparn Street, Gunnison Avenue, and the I-70B Frontage Road just north of I-70B and west of 29 Road.  The project consists of 4,400 feet of roadway construction, 1,330 feet of storm drain pipe installation, and 2,085 feet of irrigation pipe installation. Construction began on July 6 and completion of the North Phase is expected in spring 2010.

The South Phase - The contract for the South Phase was awarded to United Companies for $1,815,206. They are constructing the portion of 29 Road from D Road to D ½ Road, along with a realigned section of  D ½ Road just east of 29 Road. This project consists of 3,550 feet of roadway construction, 2,100 feet of storm drain pipe installation, and 1,910 feet of irrigation pipe installation. Construction began on July 6 and completion of the North Phase is expected in spring 2010.

The Interchange Phase - The construction contract was awarded to Lawrence Construction Company. The City received the following bids on April 20, 2010 for the 29 Road and I-70B Interchange Phase:

Firm

Location

Amount

Lawrence Construction

Littleton, CO

$19,312,363.34

SEMA Construction

Englewood, CO

$20,485,509.47

W.W. Clyde Construction

Springville, UT

$20,629,000.00

Flatiron Construction

Longmont, CO

$20,743,621.55

Concrete Express

Denver, CO

$21,445,770.32

Project Schedule
Complete
Final design and utility coordination
Complete
Utility relocation work
Complete
Right-of-way and easement acquisition
July 6, 2009 - Spring 2010
Begin construction of North & South Phase
June 2010
Begin construction of Interchange Phase
Nov 2011 Completion of project

This page updated Tuesday, August 24, 2010

Engineering Projects
Engineering Services
Real Estate
Transportation Engineering
Review Boards

Development Services

Community Planning
Neighborhood Services
Code Enforcement
Community Development Block Grant - CDBG
GJ CORE - Going Green
Historic Preservation
 
Geographic Information Systems
Download Acrobat Reader

For additional information Email or call (970) 244-1542

 

Maps - 29 Road and I-70B
29 Road and Riverside Parkway

Studies - 29 Road and I-70B
29 Road and I-70B Environmental Assessment
29 Road and I-70B Finding No Significant Impact (FONSI)

Would you like to automatically receive an e-mail notification when new 29 Road and I-70B content is published?
If so, click and press send to subscribe. You may unsubscribe at any time.
Please contact the following staff for information on the 29 Road and I-70B project at:
Paul Jagim
City Project Manager
Public Works
250 N. 5th Street
Grand Junction, CO
(970) 244-1542
Or email Paul Jagim at paulj@gjcity.org
 

Louie Dorlac

Mesa County Project Manager
29 Road & I-70B Field Office
487 29 Road (just south of the Mesa County Workforce Center)
Grand Junction, CO
(970) 244-1813
 
North Phase:
Sorter Construction
Scott Baumgardner or Bill Ogle
(970) 242-1436
 
South Phase:
United Companies
Josh Aubert
(970)243-4900
 
 
  City CouncilFire DepartmentJob OpportunitiesNews ReleasesParks and RecreationPoliceVisitor and Convention Bureau  
  City of Grand Junction, Colorado  Copyright 2001DisclaimerEmail the Webmaster